Culvert Left-hand side barrel tidy up work.
Cleaning, upstream Culvert pipework.
Permanent ventilation outlet inside the Culvert.
Permanent ventilation intake hood.
Downstream chamber Sump pump.
Pigflat demobilisation ongoing.
Operator building construction progress.
Downstream view, looking upstream.
Downstream view from the crest – cone valve commissioning and testing ongoing.
Downstream view.
Cone valve commissioning and testing, looking downstream.
Cone valve commissioning and testing.
Permanent ventilation installation progress.