January 2023

Downstream Face with concrete pour of LHS trench at cut-off wall.

Upstream Dam Face, Dam Crest & LHS Plinth – Dam Crest Survey Pins Install & LHS Plinth core holes.

Upper Spillway – Carpi Beams and Ogee grouting.

Dam Overview.

Upstream Dam Face, Dam Crest and RHS Plinth – Pull pits installed in dam crest and coring on RHS Plinth.

Upstream Face of Parapet Wall- Mobile scaffold for repairs along Nib Wall.

Along site roads – permanent stormwater drainage culverts.

Cut-off Wall – Slipforming up to the flipbucket steps.

Dam Crest – road barriers being installed.

Dam Crest Right Abutment – backfill and ducting almost complete.

Lower Spillway Bridge – preparing left abutment bridge approach road.

Right hand side Toe Berm – Preparation for the concrete pad.

Upper Spillway Rocky Knob – final concrete pour using concrete pump truck.