Building water security for our region’s future
The Mid-Year Report for the period ending 31 December 2023 is now online. It includes information and updates about health, safety and wellbeing, construction, operational readiness, and the environmental and biodiversity programme. It also provides the unaudited financial… Read More
Te Kurawai o Pūhanga, the reservoir behind the Waimea Community Dam, reached its full capacity and the spillway commenced flowing on Sunday 21 January 2024. “This is a momentous milestone for the project, and I thank all those… Read More
The Quarterly Report for the period ending 30 September 2023 is now online. It includes information and updates about health, safety and wellbeing, construction progress, operational readiness, and the environmental and biodiversity programme. It also provides an outline… Read More
The Waimea Water Ltd Annual Report for the year ending 30 June 2023 has been published. It provides an overview of the project and a summary of progress achieved in the financial year, covering the areas of health,… Read More
Waimea Water is returning to the Richmond Mall this October. From Tuesday 3 October stop in at the mall to learn more about the Waimea Community Dam, see the latest photos and videos, and pick up a physical… Read More
As the spring rain arrives, the Waimea Community Dam reservoir is starting to fill in stages. The dam is performing as expected and, with sufficient rainfall over the next few months, we expect to provide water to shareholders… Read More
Testing at the Waimea Community Dam has been progressing through the winter, and Waimea Water Ltd expects to commence filling the reservoir imminently, now that the sealing concrete plug and isolating valve have been installed. The dam, a… Read More
The Statement of Intent (SOI) for the 2023-2024 financial year is now online. The SOI provides the scope, objectives, intentions and activities of Waimea Water Ltd for the period 1 July 2023 to 30 June 2024, with forecast capital… Read More
The Quarterly Report for the period ending 31 March 2023 is now online. It includes information and updates about health, safety and wellbeing, construction progress, operational readiness, and the environmental and biodiversity programme. It also provides an outline… Read More
The Waimea Community Dam achieved an important milestone at 4pm last Friday (26 May) when the reservoir was closed, ready for filling. The Waimea Community Dam, a public private partnership between the Tasman District Council and Waimea Irrigators,… Read More